A construction company needs to remove 24 tons of dirt from a construction site. They can remove 3/4 tons of dirt each hour. How long will take to remove the dirt? Write your answer in hours.

Respuesta :

zaynah29cfc
zaynah29cfc zaynah29cfc
  • 03-10-2020

Answer: 32 hours?

Step-by-step explanation:

24 / (3/4) = 32

Answer Link

Otras preguntas

It’s question 126. Does anyone know how to solve the rest of it or if I messed up so far?
The distance between the points (5, -2) and (-7, 3) is
Given z1 = -3[tex] \sqrt{3} [/tex] + 3i and z2 = 6cos150° + 6isin150°, use complete sentences to explain why z1 = z2. Explain the steps of your work for full cr
Barry has been watching the geese that live in his neighborhood
Jesus has existed from the beginning of time with God. True False The men who followed a star to find Jesus were shepherds. True False The parable of the prodig
How many grams of Na2So4 would be formed if 0.75 moles of NaOH reacted?
Tributary of the missouri river crossword
Which of the following is an obtuse triangle ?
How do glaciers move?
What is one virulence factor that differentiates staphylococcus aureus from other species of staphylococci? what is one virulence factor that differentiates sta